COMMERCIAL CONSTRUCTION CASE STUDY

Harry's Truck Stop

Presswood served as general contractor and delivered this six-acre Charleston, Tennessee truck stop ahead of schedule despite an aggressive earthwork operation and a major unexpected buried-debris condition.

START A CONVERSATION
LocationCharleston, Tennessee
RoleGeneral Contractor
Site6 acres
Duration8 months
CompletedOctober 2024
OutcomeAhead of schedule
01

The Challenge

The property was approximately half forested and half vacant, and the schedule required roughly 20,000 cubic yards of export to be moved quickly. After earthwork began, the team uncovered an unexpected area resembling a small buried landfill, adding substantial trash and debris removal to an already demanding operation.

02

Presswood's Response

Presswood extended working hours, accelerated field production, and kept crews moving with urgency. The buried debris was excavated, removed, and properly disposed of while the team continued coordinating the building, site, utility, concrete, paving, fueling, permitting, and inspection work around the critical path.

03

The Result

Presswood completed the project ahead of schedule. The finished development includes an underground detention system, 16 regular gasoline and diesel pumps, 6 truck pumps, 26 truck parking spaces, and 27 parking spaces for regular vehicles. The client was pleased with the result and continues to hire Presswood for additional projects.

PROJECT SCOPE

From Raw Ground to Operating Truck Stop

Presswood's general-contracting and self-perform responsibilities covered the complete site-development operation and coordinated vertical construction.

  • Clearing and demolition
  • Mass grading, earthwork, excavation, and approximately 20,000 CY of export
  • Storm drainage and underground detention
  • Sanitary sewer, domestic water, fire-line, and underground utility work
  • Building, site, and exterior concrete construction
  • Landscaping, final grading, and closeout
  • Roofing, glass, MEP, and asphalt subcontractor management
  • Fueling-system specialty-contractor coordination
  • Permitting, inspections, scheduling, and project-wide trade coordination

General Contractor. Major scopes self-performed.

Presswood self-performed the major civil, site, concrete, and construction scopes while managing subcontracted roofing, glass, MEP, and asphalt work. Fuel tanks, pumps, canopy concrete, and other fueling-system work were completed by the required specialty contractor under coordinated project delivery.

  • Clearing and demolition
  • Mass grading and excavation
  • Underground detention and utilities
  • Building and site concrete
  • Landscaping and final grading
  • Subcontractor, permit, and inspection coordination